How much concrete do I need?
Length × width × depth, then a little extra.
The formula
Concrete is ordered by volume. Multiply the length by the width by the depth, all in feet, to get cubic feet. Divide by 27 to get cubic yards, the unit ready-mix plants sell by.
Depth is usually given in inches: divide it by 12 first. A 4 in slab is 0.333 ft thick, a 6 in slab 0.5 ft.
- Cubic feet = length (ft) × width (ft) × depth (ft)
- Cubic yards = cubic feet ÷ 27
- Order 5 to 10% more for waste and uneven ground
Worked examples
A 10 × 10 ft patio, 4 in thick: 10 × 10 × 0.333 = 33.3 cubic feet, or 1.23 cubic yards. With 10% extra, order about 1.36 cubic yards, or 62 bags of 80 lb.
A 12 × 20 ft driveway pad, 5 in thick: 12 × 20 × 0.417 = 100 cubic feet, or 3.7 cubic yards. That is a truck, not bags.
A footing 40 ft long, 16 in wide and 8 in thick: 40 × 1.333 × 0.667 = 35.6 cubic feet, or 1.32 cubic yards. The concrete calculator does this math for slabs and walls, the concrete footing calculator for footings.
Bags or a truck
An 80 lb bag makes about 0.60 cubic feet, so a cubic yard takes 45 bags. Up to about one cubic yard, bags are fine. Above that, ready-mix is usually cheaper and much less work, but most plants charge a short-load fee under a few yards.
For round holes and posts, use the post hole concrete calculator: it takes off the volume of the post.
FAQ
How much concrete for a 10x10 slab?
At 4 in thick, 1.23 cubic yards, or about 1.36 with 10% extra: 62 bags of 80 lb.
How much concrete for a 12x12 slab?
At 4 in thick, 1.78 cubic yards, or about 1.96 with 10% extra.
How much concrete for a 20x20 slab?
At 4 in thick, 4.94 cubic yards, or about 5.4 with 10% extra: order a truck.